UNCG campus construction updates as Fall 2019 begins

Posted on August 20, 2019

Photo of the Nursing and Instructional Building under construction

As we enter into the fall semester, here’s a breakdown of the current construction projects going on around the UNC Greensboro campus.

Nursing and Instructional Building
Pedestrian detours around the site and to Tate Street will continue through summer 2020. The building facade and interior drywall should be complete by winter break.

Progress is made on the new Nursing and Instructional Building.

South Chiller Plant
The impact of site work on Forest Street and Oakland Avenue will end by early September.

The new chiller plant near the Pedestrian Underpass.

Ragsdale Mendenhall Residence Hall
The elevator tower is under construction on the North Drive side of the building. A construction fence is in place, but no road closures are expected.

The Ragsdale-Mendenhall building.

Steam Line Replacement
An underground steam line replacement on the Mossman side of Elliott University Center is fully underway and will last through October. Construction fencing is in place. Pedestrian detours around the south side of Kaplan Commons will be in place through construction completion.

Foust Building
An electrical transformer replacement on the east side of the building will take place from October through December.

The main entrance to Foust Building.

Tennis Court Resurfacing
This project is scheduled to take place in phases starting this fall.

Stone Building Entrance Repair
This is now scheduled to begin in May 2020.

McIver Street Building Demolition
This project is near completion.

Taylor Theatre Monument Sign
This project is complete.

New signage installed for Taylor Theatre reflects the updated UNCG logo and branding.

Mossman Building
Furniture is installed and occupants have returned for the Chancellor’s area, Registrar’s Office, and Enrollment Management Office.

Bryan Building
The former Au Bon Pain area renovation will continue through fall semester. An elevator modernization project will be complete by the end of this month.

The Joseph Bryan Building.

Coleman Building
The Academic Success Center for athletes renovation will continue through fall semester.

The UNCG Dance Theatre entrance of the Coleman Building.

Campus renovations are managed by UNCG Facilities Design and Construction. For the latest construction alerts, maps, Spartan Chariot changes, and general FAQs visit their website at https://facdc.uncg.edu/alerts/

Compiled by Matthew Bryant

 